fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Implementing a risk response necessitates a change request ?

Implementing a risk response necessitates a change request ? 4 years 6 months ago #21203

  • Ihab Abdelaziz
  • Ihab Abdelaziz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Hello,
When implementing a risk response as a reaction to an identified trigger, do we still need to submit a change request? Even though the appropriate contingency reserve was previously assigned for such risk?
How to react in this situation confuses me, kindly advise.
Thanks in advance,
Ihab Abdelaziz

Implementing a risk response necessitates a change request ? 4 years 6 months ago #21205

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 473
  • Karma: 27
  • Thank you received: 146
Ihab,

Implementing a response to an identified (and therefore planned) risk does not require a change request. However, if you find your response is unsatisfactory and further response will require a change in one of the baselines, then a change request is warranted.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP

Implementing a risk response necessitates a change request ? 4 years 5 months ago #21254

  • Ihab Abdelaziz
  • Ihab Abdelaziz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Thanks Harry for your reply.

But what if the implemented response (the 1st planned response not a 2nd or further response) will affect parts of the baselines that weren't affected before implementing the response, do we still need to submit a change request?
pardon my question.

Ihab

Implementing a risk response necessitates a change request ? 4 years 5 months ago #21256

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 473
  • Karma: 27
  • Thank you received: 146
Ihab,

Should the response be unsatisfactory to cover the risk and further response will affect any baseline, a change request is required.

Perhaps a better, more broad way of thinking about it is that if anything happens to a project (or you're going to do something to a project) once the project is in motion, a change request is necessary.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP

Implementing a risk response necessitates a change request ? 4 years 5 months ago #21403

  • Ihab Abdelaziz
  • Ihab Abdelaziz's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Thats clear, thanks a lot.

Ihab

Implementing a risk response necessitates a change request ? 4 years 5 months ago #21406

  • Neha Talavdekar
  • Neha Talavdekar's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Since Risk Response is already in place appropriate cost/schedule buffers are added to the plan. So cost/schedule baseline already has it included. So no CR is needed.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login