TOPIC: Project documents and change request

Project documents and change request 4 years 7 months ago #20470

  • Kin
  • Kin's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello,
I have got across this question and I have no idea what's the answer. It is confusing somehow. (D) sounds correct but, there are new requirements added, that could mean changes on Scope which requires a change request which leaves us to (C). But, again, there are documents that do not need a change Request like Risk Register for instance, which makes (C) not the best answer? And leaves us for ( B )? I have no idea. Any help, please?
Attachments:
Last edit: by Kin.

Project documents and change request 4 years 7 months ago #20471

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
It is C

Project documents and change request 4 years 7 months ago #20472

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 473
  • Karma: 27
  • Thank you received: 146
Kin,

In general, anything that will change the scope, cost or schedule baselines will require a formal change request to be approved by the Change Control Board.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Last edit: by Harry Elston.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login