fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: How to calculate EV

How to calculate EV 8 years 4 months ago #7736

  • Twana Amin
  • Twana Amin's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 1
I wonder how to calculate EV & SV from the attached file.
Attachments:

How to calculate EV 8 years 4 months ago #7739

  • Yerikzhan Torekhanov
  • Yerikzhan Torekhanov's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 2
Earned Value = sum of planned values of completed work. So, for each activity you need to calculate value of completed work by multiplying planned value and percent completed, then sum all up.

Schedule Variance = the difference between the work completed and the work planned to be completed. SV = EV - PV.

So basicaly, when you calculate Schedule Variance, you ask yourself "I only completed so much work by now (Planned Value * Percent Complete) but should have completed that much (sum of Panned Value of all activities that should have been completed). Am I behind schedule (completed work is less than planned, SV is negative), on time (completed equals the amount of work that was planned, SV is zero), or ahead of schedule (completed more work than was planned, SV is positive)?"

Take a look at PMBOK Guide Table 7-1. Earned Value Calculations Summary Table on page 224.

Hope this helps

How to calculate EV 8 years 4 months ago #7741

  • Twana Amin
  • Twana Amin's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 1
Now I know .

EV is 500 plus 750 plus 2500 = 3750 which is calculated from the % of the PV

How to calculate EV 8 years 4 months ago #7742

  • Annie
  • Annie's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0
EV calculation:
Analysis = $500, 100% completed hence same as Planned Value(PV)
Design = $750, only 75% of PV completed
You can work out the rest and SV with EV values using the formulas.

I am not yet certified and in the progress of preparing for exam.
Could any PMP-certified member verify if this is correct?

Thanks.

How to calculate EV 8 years 4 months ago #7744

  • Mark Wuenscher, PMP
  • Mark Wuenscher, PMP's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 368
  • Karma: 1
  • Thank you received: 64
Also add the $2500 for the Development phase which is 50% completed as stated in the other responses.
Mark Wuenscher, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login