According to the PM Formulas booklet, page 7, it states how that there are two approaches for calculating ES, EF, LS and LF and how you can use the network diagram starting at either "0" or at "1", and that both of these methods will yield the same results.
However, that is not the case, depending on what is being asked. Please look at the attached .ppt file to see how using the different methods will yield different numbers for the boxes.
For example, if you were ONLY given the float activity box information:
ES = 6
DUR = 2
And asked to provide the EF, if you used the "0" method, you would end up with 8. (EF = ES + DUR)
And asked to provide the EF, if you used the "1" method, you would end up with 7. (EF = ES + DUR - 1)
Since the "0" method puts the successor's ES as the same day as the predecesor's EF, the ES numbers will always be different than using the "1" method. This isn't such a problem (except for the point made above) really, until you get to float activities, where everything breaks down. Again, see the example.
The "1" method puts the successor's ES as the day after the predecesor's EF.
I would like to see how Neelesh did this, because this demonstrates that both methods are not equal. Unless I am completely missing something...