Hi ,
Can you please advise on my query below
Scenario : There is a stakeholder who has raised a concern that his requests have not been implemented .
Options are
1) Log the issue in the issue log
2) Investigate the issue on behalf of the stakeholder
3) Capture the concern in the stakeholder register
4) Issue a change request.
My Question 1 :: If the question asks what should the project manager do FIRST , the answer is log the issue in the change log because action items to investigate , resolve and communicate start after the issue has been logged and an owner has been assigned. However, if the question says - what should the PM do first to RESOLVE the issue , would the answer still be log the issue or would it be investigate the issue ?
My question 2 :: For the same scenario above if the question says what should the PM do to resolve the issue ( Note : FIRST keyword is omitted) would the answer still be log the issue or would it be investigate the issue ?
I am trying to understand if the question asks about what to do to resolve then which option is a better choice ? Logging since its the first step when any issue arises or an option which talks about how to resolve the issue since its more directly related to the question being asked ?