Here is our free PMI-ACP Exam sample question of the week. All questions for this season will be taken from the book 'PMI-ACP Study Guide'.
Question 126: What is the main difference between a burn down and burn up chart?
A. A burn down chart tracks the time and effort left, and a burn up chart tracks completed work and changes.
B. A burn up chart tracks the time and effort left, and a burn down chart tracks completed work and changes.
C. A burn down chart tracks risk averted, and a burn up chart tracks risks left to manage.
D. A burn down chart tracks the burn rate of project costs, and a burn up chart tracks scope of work left to complete.