fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: PMI-ACP Question/Topic of the week : Season-8

PMI-ACP Question/Topic of the week : Season-8 3 weeks 2 days ago #32127

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 313
  • Karma: -1
  • Thank you received: 7
Here is our free PMI-ACP Exam sample question of the week. All questions for this season will be taken from the book 'PMI-ACP Study Guide'.

Question 126: What is the main difference between a burn down and burn up chart?
A. A burn down chart tracks the time and effort left, and a burn up chart tracks completed work and changes.
B. A burn up chart tracks the time and effort left, and a burn down chart tracks completed work and changes.
C. A burn down chart tracks risk averted, and a burn up chart tracks risks left to manage.
D. A burn down chart tracks the burn rate of project costs, and a burn up chart tracks scope of work left to complete.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 2 weeks 5 days ago #32136

  • Esther Butler Conduah
  • Esther  Butler Conduah 's Avatar
  • Away
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
The answer is A.

PMI-ACP Question/Topic of the week : Season-8 2 weeks 1 day ago #32139

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 313
  • Karma: -1
  • Thank you received: 7
That's the right answer.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 2 weeks 1 day ago #32140

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 313
  • Karma: -1
  • Thank you received: 7
Correct Answer to Q#126: A

A burn down chart is used to show how much work has been completed, and it can help the team determine how much time the project will take. A burn up chart tracks work completed, but it also shows changes in scope and how that affects the ideal burn.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 2 weeks 1 day ago #32141

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 313
  • Karma: -1
  • Thank you received: 7
Here is our free PMI-ACP Exam sample question of the week.

Question 127: Your team has determined that there are 500 points of functionality left in the backlog to complete. The first 4 iteration’s velocity has been tracked as follows:
20 points, 35 points, 55 points, 50 points
Approximately how many more iterations will it take to complete the project based on velocity?
A. 12.5
B. 10
C. 14.7
D. 16
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 1 week 1 day ago #32160

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 313
  • Karma: -1
  • Thank you received: 7
Correct Answer to Q#127: A.

To determine how many iterations remain, the team would take an average of all of the iterations and divide it into the remaining points. In this case, the team would probably round up to 13.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 1 week 1 day ago #32161

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 313
  • Karma: -1
  • Thank you received: 7
Here is our free PMI-ACP Exam sample question of the week.

Question 128: A key stakeholder has asked for information on the team’s progression through the iteration. What would be the best way to present information about the team’s progress?
A. Earned value report
B. Burn down chart
C. Detailed notes on stand-up meetings
D. A Gantt chart
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 13 hours 32 minutes ago #32183

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 313
  • Karma: -1
  • Thank you received: 7
Correct Answer to Q#128: B

Burn down, burn up, or velocity tracking charts are the best information radiators to present information on performance.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMI-ACP Question/Topic of the week : Season-8 13 hours 31 minutes ago #32184

  • Sameer Menda
  • Sameer Menda's Avatar Topic Author
  • Offline
  • Moderator
  • Moderator
  • Posts: 313
  • Karma: -1
  • Thank you received: 7
Here is our free PMI-ACP Exam sample question of the week.

Question 129: You are working on a large project, and many of your team members are going to be virtually distributed. What is the best way to help your virtual team be successful for your upcoming project?
A. Distributed teams are not recommended on Agile projects.
B. Set up ground rules.
C. Set up a live stream of video feeds to keep everyone virtually colocated.
D. Co-locate the team for the planning meetings and two iterations if possible.
Sameer Menda | PMP, PMI-ACP, PSM II
Community Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinSameer MendaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login