Hi All,
Can someone please clarify on below?
Question 1) A project is in the final stage of testing when it receives a major change request from the customer. This would delay the final delivery of the project by 2 weeks. What should the Project Manager do NEXT?
SELECT THE CORRECT ANSWER
A) Create a change request and go through the change management process
Evaluate the impact of the change
C ) Communicate the implication of the change to the customer
D) Adjust the project management plan and baseline
According to me Answer should be "B" as we need to evaluate on other triple constraints as well(In question impact evaluated only on schedule).But Correct answer is "C". how ?
Question 2) A Project Manager working on a critical deliverable encounters a major change that affects the schedule baseline and the next milestone deliverable. This change cannot be accommodated within the current project management plan. What is the BEST option for the Project Manager?
SELECT THE CORRECT ANSWER
A) Avoid the change as it gravely affects the project deadline
Explore options to reduce the effect of change
C) Communicate the implication of this change request to the customer
D) Seek approval from change control board or project sponsor
Correct answer is "D" why should not be "C" or"B" as in above 1st question we communicate the effect of change to customer or Explore options to reduce the effect of change.
Question 3) A Project Manager has just finished a Gantt (bar) chart representing the project schedule. Which of the following documents does NOT get updated?
SELECT THE CORRECT ANSWER
A) Activity Resource Requirement
Risk Register
C) Resource Leveling
D) Calendar
Why correct answer is "C"