TOPIC: Procurement in Close project or phase ?

Procurement in Close project or phase ? 4 years 5 months ago #21392

  • Neha Talavdekar
  • Neha Talavdekar's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Procurements are closed in Control Procurements process (M&C) then why Close Project or phase process has activities related to completion of contractual agreements (finalizing open claims/confirming formal acceptance of seller work etc) ?

Procurement in Close project or phase ? 4 years 5 months ago #21397

  • Denver Martin
  • Denver Martin's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 15
  • Karma: 2
  • Thank you received: 6
When you have multiple vendors/sellers, closing procurements can occur throughout the project during the executing/monitoring and controlling phase as vendor's satisfy contractural requirements and deliver what was promised. Contracts need to be finalized and final invoices paid in a timely manner during this time where you may not have reached project closure yet.

And then once the project's deliverables are completed and the project moves to the closing phase, there still might be open contracts that haven't yet been finalized, invoices still need to be paid, level of quality still needs to be confirmed, etc. So basically closing out procurements may occurs in both phases but it's listed as an activity within 4.7 Close Project or Phase rather than a duplicate process. And also remember 4.7 is an integration process so it can touch upon elements from the other processes.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login