TOPIC: Change Requests

Change Requests 4 years 5 months ago #21391

  • Gen Welsing
  • Gen Welsing's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello all,
I have a pressing question that I can't seem to settle on a response to, and I am hoping you can help me process it. The Org. procedure requires only the CCB
to approve all change requests (that impact the baselines) of this project. The CCB meets every other month, and the PM has a change request that impacts the cost baseline (and the schedule's); it needs the CCB's review asap because the project has 3 weeks to go and is already behind schedule. His options are to:
- Escalate to the project sponsor
- Wait for the CCB to meet next month
- Approve the request, document it and notify the stakeholders
- Find other individuals named in the pm plan and org. procedures who have the authority to approve change requests that don't impact baselines (to see if it is okay to make an exception to approve this due to the extenuating circumstances, maybe)

Any thoughts on which action is the most appropriate and why?
Thank you!

Change Requests 4 years 5 months ago #21393

  • Pierre Paris
  • Pierre Paris's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Thank you received: 0
Hi Gen,
I would go to Sponsor as CR is important for project, CCB is not available and it's sponsor's responsibility to help you out..

Hope it helps....

Change Requests 4 years 5 months ago #21409

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
Thank you for the assistance, Pierre.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login