fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Explanation

Explanation 4 years 5 months ago #21314

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
How did they get this answer?

A project was planned to take 5 months. The team is currently 3 months into it and has completed half of the work.

Applying Earned schedule technique, what are the performance data of the project?


SV: -0.5 months, SPI: 0.83
SV: 1.5 months, SPI: 1.5
SV: -2,5 months, SPI: 0.83
SV: 0.5 months, SPI: 1.83

Explanation 4 years 5 months ago #21327

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 473
  • Karma: 27
  • Thank you received: 146
Anon:

This is one of the questions that look like a math question bu really isn't as long as you know the definitions of all the performance indices and variances.

The project is 50% complete and 60% into the schedule. It is BEHIND Schedule - therefore the project's SPI is less than 1. Therefore only A or C can be correct.
In terms of time they are at 2.5 months worth of earned value but they have burned 3 months of Planned Value. Therefore they are -0.5 months in Schedule Variance.

The answer is A

Hope that helps.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Last edit: by Harry Elston.

Explanation 4 years 4 months ago #22422

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
Let me explain.
We have completed half the work. As per the plan, 100% work <=> 5 months
So, 50% work <=> 2.5 months

2.5 months is the Earned Schedule.
3.0 months is the Actual Time.

Accordingly,
SV = ES - AT = -0.5 months
SPI = ES/AT = 0.83

A is the correct choice.

If you wish to understand the basics of Earned Schedule, have a look at this lesson.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login