fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Activity duration range estimate with standard deviation

Activity duration range estimate with standard deviation 4 years 6 months ago #20919

  • Ruby F
  • Ruby F's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hi guys - same again, my exam is tomorrow and I have a quick question.

With calculation the range of estimated duration +- standard deviation, if we get a question like this on exam how do we know whether to use the triangular formula or the PERT formula.

Thanks to anyone

Activity duration range estimate with standard deviation 4 years 6 months ago #20935

  • Eric Wanyutu Kahiga, PMP, PMI-ACP
  • Eric Wanyutu Kahiga, PMP, PMI-ACP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 84
  • Karma: 4
  • Thank you received: 28
Hi Ruby.

Usually, the exam question will state which method to use.

Once again, I wish you the very best in your exam.
Eric Wanyutu
The following user(s) said Thank You: Ruby F
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login