I came across this question on another forum, and it is not from Cornelius' material. However, I would like to a) know what the forum thinks the right answer to be
b) Cornelius' view if possible about such type of questions, and hopefully the correct answer as well. Here goes..Any help is appreciated.
Rebecca is managing a Beach Resort project. The project has an imposed deadline and hence the schedule is very aggressive. Some cyclones are expected to hit the area where Rebecca and her team are working and that may delay one of their major milestones. They will get 3 to 4 days of warning if the cyclone is going to arrive. In that case, Rebecca has planned to move her team out to a safer place and do interior design plans that are actually scheduled one month later. This way, they may still be able to meet the milestone. What can Rebecca’s Risk Response Plan be termed as?
a. Contingent Response Strategy.
b. Avoiding.
c. Mitigating.
d. Transfer
----
Source says correct answer is a! Have to admit, i first thought a and then thought C. Not sure.