Can someone please explain in further details why option C "Scope Statement " is not the correct option for the question below? I thought that because Scope Statement is an input to produce the WBS is would be used here to help produce it. The correct answer seems tricky to me since there are not OPAs but then the PM is supposed to find it outside the company., I guess the same would apply to Lessons Learned wouldn't it?
Anyway, I would like to read some opinions about this question and the answer given.
Question 13: A project manager is managing a process improvement project based on the Six Sigma process improvement methodology. The Six Sigma methodology is being tested for the first time in the company. In addition, this is the first time the project manager is managing such a project. The project manager wants to create the project’s WBS, but there are no Six Sigma organizational process assets available. Which of the following would help the project manager create the project WBS?
A.) Lessons learned
B.) WBS templates
C.) Scope statement
D.) Decomposition
Correct answer is B
Explanation: The required knowledge does not currently exist in the company. The project manager must look for external sources for this information. WBS templates can be very helpful to the project manager when drafting this project's WBS.
A.) Incorrect. As this company has not done this before, so there are no lessons learned
B.) Correct. WBS templates can be found from a variety of sources inside and outside the company.
C.) Incorrect. The scope statement is an output of the Define Scope process and will not help in this manner.
D.) Incorrect. Decomposition is the process of creating the WBS. It does not define the structure.