fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Risk Response

Risk Response 4 years 9 months ago #19849

  • Anantha Narayanan Santhanagopalan
  • Anantha Narayanan Santhanagopalan's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 39
  • Karma: 3
  • Thank you received: 7
Does Project Manager need to submit change request to implement a risk response for which he already has a contingency reserve allocated?

To my knowledge, if a risk for which we already have a risk response plan we need not go through change request to use contingency reserve. Can anyone confirm please?

Risk Response 4 years 9 months ago #19850

  • googlesmart
  • googlesmart's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Karma: 1
  • Thank you received: 10
Correct, if it is identified risk.
The following user(s) said Thank You: Anantha Narayanan Santhanagopalan
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login