Need help with a Quick Question... 4 years 10 months ago #19464

  • Christian Bass
  • Christian Bass's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0
Is a Responsibility assignment matrix an output of any of the processes?
I can find definitions and examples but I'm not sure where this comes from in the grand scheme of things.

Thanks.

Need help with a Quick Question... 4 years 10 months ago #19469

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 473
  • Karma: 27
  • Thank you received: 146
Christian,

No. It is a tool/technique of "Plan Resource Management." (PMBOK 6th ed, page 312 is the first mention of the RAM).

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login