fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: What's EMV (BEFORE COSTS)?

What's EMV (BEFORE COSTS)? 5 years 16 hours ago #19170

  • Eric Hu
  • Eric Hu's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Thank you received: 1
On PMBOK page 435, in Figure 11-15, below EMV calculation of "Build New Plant" there is a parenthesis mentioning "before costs".
What does "before costs" mean? in Net Path Values it actually considers cost by subtracting investment($120M), so I think it should be "after costs".
Any suggestions?
Attachments:
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login