TOPIC: What's the difference between bottom up estimate and cost aggregation

What's the difference between bottom up estimate and cost aggregation 5 years 2 months ago #18431

  • RBA
  • RBA's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
What's the difference between bottom up estimate and cost aggregation

What's the difference between bottom up estimate and cost aggregation 5 years 2 months ago #18433

  • James Keuning
  • James Keuning's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Karma: 1
  • Thank you received: 4
I’ll take a stab at this - cost aggregation is just adding up different costs. So cost aggregation is a step taken during bottoms up estimating. When you identify the costs during the bottoms up method you aggregate them to come up with one number for the cost/budget.

In fact the definition of bottoms up in the pmbok says pretty much this.

Bottom-Up Estimating. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).

The following user(s) said Thank You: Ahmad Jaber
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login