fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Difference between term cost and budget

Difference between term cost and budget 5 years 3 months ago #18287

  • Michelle Navarro
  • Michelle  Navarro's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 10
  • Thank you received: 2
Does PMI want us to use “cost” or “budget”?

As I’m studying and listening to the Prepcasts, it seems that Cost is usually used. However, a email last week used the term “budget” in the lesson, but the correct answer to the test question used the term "cost."

This is from the email: The A Guide to the Project Management Body of Knowledge (PMBOK® Guide) mentions six competing project constraints. Namely: Scope, Quality, Schedule, Budget, Resources, and Risk.

This is the sample question and answer:

Which of the following are the project constraints?
A.) Scope, Schedule, Budget, Personnel, Quality, Risk
B.) Scope, Schedule, Budget, Resources, Quality, Risk
C.) Scope, Schedule, Cost, Resources, Quality, Risk
D.) Scope, Schedule, Cost, Personnel, Quality, Risk

I picked answer B because it matched the email. However, the email said: C.) is correct. The competing project constraints that you as the project manager must balance are Scope, Quality, Schedule, Cost, Resources, and Risk.

I'm confused

Difference between term cost and budget 5 years 2 months ago #18378

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99
Hello Michelle,

I have to agree that C is correct.

If I remembered correctly, the term budget was replaced with cost in the recent PMBOK revision. If you encounter similar questions in the future, always go with cost.
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
The following user(s) said Thank You: Michelle Navarro
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login