fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Change Request or No Change Request For Project Document Updates

Change Request or No Change Request For Project Document Updates 5 years 4 months ago #17829

  • John Bacon
  • John Bacon's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I had a question on the practice exam that asked me what I should do next and I had to choose between the option of updating a project document, I think it was the schedule, or to submit a change request. I chose the option to submit a change request since a change would be necessary to modify the current schedule. I got the answer wrong however, that the correct answer was to update the schedule with the rationale that since the baseline wasn't being changed, a change request is not required. So when should a change request be done? Only when a part of the project management plan needs to change or when updates to project documents need to be made as well?

Change Request or No Change Request For Project Document Updates 5 years 4 months ago #17834

  • Donald Terry
  • Donald Terry's Avatar
  • Offline
  • Administrator
  • Administrator
  • Posts: 30
  • Karma: 1
  • Thank you received: 10
Hi John,

Change management is an important concept to master in preparation for the PMP exam. Not only will you see a fair number of questions specifically on change management, but you will also likely encounter questions where understanding when a change request is required will help you eliminate incorrect answer choices (as is the case in your example).

1. Before the project has been baselined (project management plan has been approved) change requests are not required to modify any project artifact. See page 115 of the PMBOK® Guide.

2. Project artifacts that are placed in configuration control are recorded in the configuration management plan. Placing a project element in configuration control simply means that an approved change request is required for modification. See page 115 of the PMBOK® Guide.

3. Project baselines are always considered configuration elements. The rationale is that the baselines are the most fundamental aspect of the project, and if the baselines are not controlled, then a change management plan does not exist. Not having a change management plan would be contradictory to project management best practices. See page 115 of the PMBOK® Guide.

4. The project management plan is typically a controlled document. Unless the question suggests otherwise, we assume the project management plan is placed in configuration control.

5. Project documents are not typically placed in configuration control. Unless the question suggests otherwise, we assume that project documents are not considered configuration elements.

In the example you cite, the project schedule is a project document. Therefore, unless it is implied in the question that the project schedule has been placed in configuration control, then a change request is not required to be submitted prior to modification. If the schedule baseline where to be impacted, then an approved change request would be required to modify the schedule baseline.
Donald Terry, MBA, PMP, PMI-ACP

Full disclosure: I work for OSP International as an independent contractor
The following user(s) said Thank You: VP, Hakooma Mudenka, Mario Sorrentino
Last edit: by Donald Terry.

Change Request or No Change Request For Project Document Updates 4 years 9 months ago #19959

  • VP
  • VP's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Great explanation Donald, thank you! So if an OPA needs to be updated (for example, as output of Control Procurements), is a Change Request required? If not, can an OPA be placed in configuration control or does configuration control only have project-specific artifacts?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login