TOPIC: RACI Chart and resource break structre

RACI Chart and resource break structre 5 years 5 months ago #17752

  • Hossam
  • Hossam's Avatar Topic Author
  • Visitor
  • Visitor
Hello,

I'm a bit confused about RACI Chart and Resource break down structure, and why they are used in the planning resource process. At the stage of Planning resource, I still do no know what resources i should assign yet, let go having RACI chart or Resource break down structure. Can someone please explain? thanks

RACI Chart and resource break structre 5 years 5 months ago #17768

  • Donald Terry
  • Donald Terry's Avatar
  • Offline
  • Administrator
  • Administrator
  • Posts: 30
  • Karma: 1
  • Thank you received: 10
Hi Hossam,

A RACI chart is created as an output of the Plan Resource Management process, and the resource breakdown structure is developed as an output of the Estimate Activity Resources process. You will make resource assignments as part of the planning processes using the stakeholder register and other inputs to make these resource assignments. Once these documents are completed, they can serve as inputs to other processes including planning processes. For example, the resource breakdown structure serves as an input to the Estimate Activity Durations process. I think it helps to think of the processes in terms of inputs and outputs to understand how the project management plan is developed.
Donald Terry, MBA, PMP, PMI-ACP

Full disclosure: I work for OSP International as an independent contractor
Last edit: by Donald Terry.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login