-
Yazmine Darcy
-
-
Away
-
Administrator
-
-
Posts: 35
-
Karma: 12
-
Thank you received: 23
-
-
|
Hello Nathan,
Thank you for your follow-up question. At that time, the question was first raised, it was resolved but a response was posted in this forum.
If you are viewing The PM Prepcast on the Learning Management System, you would have seen the following comment on the Earned Value lesson.
If you downloaded The PM Prepcast lessons and watching them on a personal device, then you may not have seen it.
"Please note:
According to the Practice Standard for Earned Value Management, Second Edition, 2011, Project Management Institute, Inc., there are three different methods to calculate the earned value: discrete effort, apportioned effort, and level of effort. The discrete effort method, in turn, is subdivided into four principal measurement methods: a fixed formula, weighted milestone, percent complete, and physical measurement. The selection of the method is determined by several factors, such as the type of the project, phase of the project, type of work package, etc.
The calculation of the earned value in the construction example used in this lesson is based on the physical measurement method. In this method, the value is considered earned when a specific work package is fully completed. Some questions in our PM Exam Simulator, however, use the percent complete measurement method, in which the value is earned in proportion to the percent of work completed on a work package."
I hope the above clarifies things for you.
--
Yazmine Darcy, MBA, PMP, PMI-ACP, CSM
Director of Operations, OSP International LLC
The Project Management PrepCast™ -
www.project-management-prepcast.com
|