TOPIC: Change Request process

Change Request process 5 years 5 months ago #17605

  • Daniel Kokkos
  • Daniel Kokkos's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 30
  • Thank you received: 0
Hello Prepcast,

In the Prepcast questions the questions on Change Requests have me trying to understand the steps in a change request. It shows that it is important to document the change request as having a record of it first. In a recent Dan Ryan webinar we saw a question that there was a change request but it required an evaluation/analysis first. SO Which is it? Or does it depend. I know analysis is important but also documenting and getting a written formal record is also important. Could anyone provide an overview of how to process a change request. Does it depend on the person submitting it? If it was submitted already by another stakeholder, what would you do? Change log? Eval?

I know this is VERY important to understand for the test and I am sure it has been posted here prior but I couldn't find it.

EX - Document change request, record change log, analysis, etc.

Change Request process 5 years 5 months ago #17631

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99
Hi Daniel,

Let's use an example, see if this will make you understand better.

In a software project, a change request is submitted to have a new function added.
1. PM records it in the change log
2. PM reviews the change request, evaluates the impact of the change
3. PM then identifies options (ex. look at alternatives/workarounds)
4. PM gets the change request approved internally (ex. Through CCB)
5. Get customer buy-in (if required)
6. Updates change log

Source: Rita v9 Pg 161 + some of my interpretations.
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin

Change Request process 5 years 5 months ago #17646

  • Daniel Kokkos
  • Daniel Kokkos's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 30
  • Thank you received: 0
Thanks Joe. So what you are basically saying is to submit the change request first in most cases. I think I am in that boat as well, but I don't want to get stumped when I get a question on this during the exam. Rita states Evaluate the impact, identify options, get the change request approved, get customer buy in. This is high level.
Last edit: by Daniel Kokkos.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login