fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Basis of estimates vs Cost Estimates

Basis of estimates vs Cost Estimates 5 years 6 months ago #17510

  • Jessica Aweya
  • Jessica Aweya's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello,

What is the difference between the basis of estimates, cost estimates and duration of estimates?

Thanks

Basis of estimates vs Cost Estimates 5 years 5 months ago #17579

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
Basis of estimates = how the cost is derived.
Cost estimates = the estimated cost that are included to complete an activity.
Duration estimates = the estimated time period required to complete an activity
The following user(s) said Thank You: Joann Sosa, Divya Singh
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login