Where, or in what process, is the performance measurement baseline set/developed? I understand it is a part of the project management plan, however, is this set by project sponsor?

PMB 5 years 6 months ago #17519

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
Performance measurement baseline (PMB) are the 3 baselines combined: Scope, Schedule and Cost. Each of these baselines are performed in their respective processes and then integrated into "Develop Project Management Plan" process. PMB gets updated as the project progresses.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login