TOPIC: Work packages VS Define activites

Work packages VS Define activites 5 years 6 months ago #17411

  • Gaurav Saxena
  • Gaurav Saxena's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 27
  • Thank you received: 0
Hi All,
looking for another understanding on Work packages ( which is lowest package of WBS ) and activity . Work package is not a activity ? or it is group of activity ? Kindly help.

Thanks

Work packages VS Define activites 5 years 6 months ago #17500

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
PMBOK page 181 stated the key benefit for Define Activities process is that "it decomposes work packages into schedule activities...", therefore, it is a series of activities to complete the work package. For example, you have a work package called "Chapter 5 Project Scope Management Exam Readiness" and the activities are:
1. Listen to PrepCast for section 5.1 to 5.6
2. Read PMBOK for section 5.1 to 5.6
3. Do exam questions for Chapter 5
4. Revise incorrect questions

Hope this explanation helps.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login