TOPIC: Why 6.2 Define Activities does not require WBS or project charter as input?

Why 6.2 Define Activities does not require WBS or project charter as input? 5 years 6 months ago #17330

  • Edmund Fong
  • Edmund Fong's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Karma: 1
  • Thank you received: 1
As title

Why 6.2 Define Activities does not require WBS or project charter as input? 5 years 6 months ago #17402

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
WBS is in the Scope Baseline (refer to PMBOK page 161). Scope Baseline is the approved version of the scope statement, WBS and the WBS dictionary. Scope Baseline is an input to Define Activities.

A project charter has the summary milestone schedule (refer toPMBOK page 81) which is used as an input to Plan Schedule Management process. Schedule Management Plan is one component of the Project Management Plan which is an input to Define Activities.
The following user(s) said Thank You: Edmund Fong
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login