TOPIC: Change requests for schedule compression techniques

Change requests for schedule compression techniques 5 years 6 months ago #17218

  • Ben Chalfie
  • Ben Chalfie's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 0
Do you need to submit change requests for both fast-tracking and crashing, or only when those techniques will change the schedule baseline and perhaps other constraints?

Change requests for schedule compression techniques 5 years 6 months ago #17261

  • Cynthia Lim Louis, PMP
  • Cynthia Lim Louis, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 84
  • Karma: 5
  • Thank you received: 21
You only need to submit change requests when there is a variance between planned vs. actual performance that impact your baselines. In your change request, you can indicate what technique you are using to bring your baselines back.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login