Where do we account for Residual Risk Cost? is it part of Contingency reserve or management reserve? Chapter 11.5

Residual Risk Cost 5 years 8 months ago #16879

  • Syed Farhan Qadri
  • Syed Farhan Qadri's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 6
  • Thank you received: 0
Residual risk is known. We use Contigency reserves, if it occur. Management reserve is for unknown risk, which didn't identified in the Identify risk process. Hope it help you.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login