fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Contract closure

Contract closure 5 years 9 months ago #16454

  • Julia Soligo
  • Julia Soligo's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 11
  • Thank you received: 0
Hello,

According to PMBOK, is it correct to assume that contracts with SELLERS are closed during Control procurement process, while contracts with CUSTOMERS are closed during Close project or phase process?

Also, during Close project or phase process, is the task of Closing the contract with the customer the last thing to do? or is it the Administrative closure? I'm a bit confused about which tasks would be outside of Administrative closure, as PMBOK only describe the tasks for Administrative closure (page 123).

Thanks!
Julia

Contract closure 5 years 9 months ago #16456

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99

Julia Soligo wrote: Hello,

According to PMBOK, is it correct to assume that contracts with SELLERS are closed during Control procurement process, while contracts with CUSTOMERS are closed during Close project or phase process?

You are correct

Also, during Close project or phase process, is the task of Closing the contract with the customer the last thing to do? or is it the Administrative closure? I'm a bit confused about which tasks would be outside of Administrative closure, as PMBOK only describe the tasks for Administrative closure (page 123).

According to the PMI Exam Outline, the Admin Closure is under task #3

Thanks!
Julia

Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin

Contract closure 5 years 9 months ago #16458

  • Julia Soligo
  • Julia Soligo's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 11
  • Thank you received: 0
And when would you finally close the contract with the customer, after the administrative closure or before? Which tasks would be outside the administrative closure?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login