Cuong C. Do wrote: Please help me with my PMI PMP application experience worksheet, I am hoping to not have any red flags and lessening my chances of an audit. Thank you in advance.
This is the detail I wrote for one of my experience titled: "VIP English Lesson Plans Package"
Project duration, total of 13 months, hours for each KA:
Initiating the Project- 60.00
Planning the Project- 250.00
Executing the Project- 600.00
Controlling and Monitoring the Project- 600.00
Closing the Project- 70.00
The draft of my Description:
Project objective: Produce Lesson Plan Package for VIP clients
IN: Developed Project Charter. Identified stakeholders.
PL: Developed a project management plan. Planned scope and schedule management.
This looks a bit redundant to me, since scope/schedule management plans are part of the project management plan
EX: Worked on the lesson plans with Learning Consultants. Managed stakeholder engagement.
"Working on the deliverable" is not part of a PM's responsibility, do you mean "Directing a group of consultants to work on the lesson plans?"
MC: Checked the quality of the lesson plans. Controlled schedule.
"Performed quality control" would be a better wording, this is just my opinion.
CL: Submitted deliverables and began closing project.
As the Project Leader, my responsibility was to manage the production of a VIP Lesson Plan Package. I accomplished this by the scheduled deadline.
Sorry if my comments look a little harsh. My main goal is to reduce the chance of re-sending your application so that you can begin your exam prep asap. These are all my personal suggestions and it is up to PMI to determine if you are eligible or not. I would also suggest going over the PM course material again to get yourself familiar with the PMI knowledge areas.