fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Change control steps/process [Imp. to solve all CR questions]

Change control steps/process [Imp. to solve all CR questions] 5 years 10 months ago #16310

  • Paramjeet Nagpal
  • Paramjeet Nagpal's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Please verify my understanding on CR steps:

a. Identification of change
b. Documentation of Change (Request) in the change log.
c. Impact analysis of changed.
d. Presentation of Change Request (CR) to Change Control Board (CCB)
e. The decision on CR by CCB
f. Update Changelog.
g. Communicate/Inform the decision to Stakeholders .
(If approved)
h. Implementation of Approved CR.


Need Clarification post (e)

Change control steps/process [Imp. to solve all CR questions] 5 years 10 months ago #16315

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99
Hi Paramjeet,

That is nicely written, I don't think there is anything wrong with it. Maybe you can add "Change log update to reflect the results of the implementation" at the end.

Cheers
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
The following user(s) said Thank You: Paramjeet Nagpal

Change control steps/process [Imp. to solve all CR questions] 5 years 10 months ago #16325

  • Pingping Wen
  • Pingping Wen's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 2
I would add:
  • document issue in Issue log- assign person who/when/how look after the issue
    Analyze the issue- whether or not issue become a change request
    then :
a. Identification of change
*** Submit Change request*** only related baselines/project management plan;
b. Documentation of Change (Request) in the change log.
c. Impact analysis of changed.
d. Presentation of Change Request (CR) to Change Control Board (CCB)
e. The decision on CR by CCB
f. Update Changelog.
g. Communicate/Inform the decision to Stakeholders .
(If approved) *** also not approved needs to notify stakeholders as well***
h. Implementation of Approved CR.
The following user(s) said Thank You: Paramjeet Nagpal

Change control steps/process [Imp. to solve all CR questions] 5 years 10 months ago #16330

  • Paramjeet Nagpal
  • Paramjeet Nagpal's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Thanks a lot Joe and Pingpang !! I have an exam next week.

Change control steps/process [Imp. to solve all CR questions] 5 years 10 months ago #16331

  • ABSY KRDEY
  • ABSY KRDEY's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 8
  • Thank you received: 1
Hello,
It is good I think.
I would add before h. :
update to plans, baselines, etc.
I would also add after h.:
conduct approved change request review and update with validated changes (Control Quality process)
The following user(s) said Thank You: Paramjeet Nagpal
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login