fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Close Project

Close Project 5 years 10 months ago #16240

  • Judy Patterson
  • Judy Patterson's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Can anyone tell me what the last step of Close Project would be? I did a sample test with a question on this topic and the correct answer was "Finalize and close procurements". Does this seem correct?

Close Project 5 years 10 months ago #16241

  • Pingping Wen
  • Pingping Wen's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 2
it is not correct. Close procurement is in Control Procurement process.
Project Close:
Final confirm the accepted deliveries
Issue Final report
Lesson Learned Repository
Achieve project info/docs
Update OPA
Stakeholder's evaluation project
Last step: dismiss the project team

Due to 5th and 6th version of PMP changing, a lot of training materials have not been updated. Above are I have learned /summarized from two training course materials of version 6 of PMP. Hope it is helpful!
I failed my first try in last March but PMP version was 5th, I now prepare my 2nd time try and PMP version is the 6th. Wish all the best and supper good luck to all of us who study hard and plan to pass the exam.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login