Thanks for the information Joe.
I have another question; scheduling and EVA have been the toughest topics for me. I have spent the past few days focusing solely on these 2 concepts. I actually feel that the information is finally coming together. I still have an issue understanding the difference between float and leads and lags? I understand, that float is based purely on the critical path and is the difference between the forward and backward paths. I also understand the difference between total and free float. My issue rests in the fact that the definitions for float, leads, and lags basically read the same and as a result why are leads and lags not part of the duration estimates? Can you please explain the difference between leads, lags, and float. Also, when to use leads and lags and why they are not part of duration estimates?
Sorry for the complicated description.
Thanks, Adam