fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: TCPI formula

TCPI formula 5 years 11 months ago #15871

  • Cyril Galland
  • Cyril Galland's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0
Why should we use the TCPI "based on EAC" = BAC-EV / EAC-AC when our CPI is over budget ?

Doing so we will have a TCPI with the same value of the CPI (<1) and won't take any corrective actions to bring the budget back to track. Or does it imply that the EAC has been approved as the new baseline ?

Thx !!!

Cyril

TCPI formula 5 years 11 months ago #15882

  • Lillian Li
  • Lillian Li's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
PMBoK P266. If it becomes obvious that the BAC is no longer viable, the project manager should consider the forecasted EAC. Once approved, the EAC may replace the BAC in the TCPI calculation.

TCPI formula 5 years 11 months ago #15920

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
Thx you !!!
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login