TOPIC: Question - Please answer

Question - Please answer 6 years 1 month ago #15286

  • Vikas
  • Vikas's Avatar Topic Author
  • Visitor
  • Visitor
Q:4-You are managing an educational research project and three separate project teams work for you. Each team consists of four engineers and a team lead. There is no need for cross-team communications because every person only needs to communicate within their own team. Only the team leads report directly to you and when information needs to be distributed from one team to another, this also goes through you. What is the total number of communication channels used on your project?

Option are - 36, 33, 30 and 120

Can anyone answer with explanation?
Last edit: by John Paul Bugarin.

Question - Please answer 6 years 1 month ago #15287

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 621
Vikas, please tell us where you found this question. Who created/owns it?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Question - Please answer 6 years 1 month ago #15288

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99
This is an interesting question, I will try to answer it.

There are two calculations needed, one for the project teams, and the other one between the PM and team leads.

See image below



Each team has 10 communication channels, and 3 teams would equal to 30. Plus the 6 channels between the PM and team leads. The total would be 36.
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
The following user(s) said Thank You: AC

Question - Please answer 6 years 1 month ago #15295

  • Arindam Das
  • Arindam Das's Avatar Topic Author
  • Visitor
  • Visitor
The answer is 33. For each team the channel of communication is 10 (5x4/2). For three teams it adds upto 30. Now the team leaders interaction to other team leaders is through Project Manager and there is only one channel of communication between Project Manager and each team leader. This totals upto 3. Therefore the total channel of communication is 33 (30+3)

Question - Please answer 6 years 1 month ago #15298

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 26
  • Thank you received: 99

Arindam Das wrote: Now the team leaders interaction to other team leaders is through Project Manager and there is only one channel of communication between Project Manager and each team leader. This totals upto 3. Therefore the total channel of communication is 33 (30+3)


I'll have to disagree on this part. The question states "Only the team leads report directly to you and when information needs to be distributed from one team to another, this also goes through you", therefore it indicates a 4-way communication between the PM and 3 team leads.
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login