fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Need help on Oliver Lehmann Question

Need help on Oliver Lehmann Question 15 years 1 month ago #746

  • Praveen Kumar
  • Praveen Kumar's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 10
  • Thank you received: 0
Hi,

Regarding following question,

Post-mortem analysis of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?
o The project was terminated early. At that time, it was over budget and ahead of schedule.
o The project has produced additional deliverables which were originally not required.
o The project has evidently been finished under budget and behind of schedule.
o The project has evidently been finished over budget and ahead of schedule.

By all means it can be said that the project is over budget and ahead of schedule based on rules but i am unable to understand what make option 1 as right answer instead of 4.

Please help.

Praveen Kumar
Last edit: by Praveen Kumar.

Re:Need help on Oliver Lehmann Question 15 years 1 month ago #752

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1997
  • Karma: 121
  • Thank you received: 619
Praveen,

Where does this question come from? I don't think this is one that is provided in our materials, right?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Need help on Oliver Lehmann Question 15 years 4 weeks ago #791

  • Praveen Kumar
  • Praveen Kumar's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 10
  • Thank you received: 0
HI Cornilius,

This question is from Oliver lehmann as the topic says but never mind i got the answer for it and moreover i got the PMP certifications as well yesterday. Lessons learnt are posted soon.

You are the man behind my success.

Praveen kumar

Re:Need help on Oliver Lehmann Question 15 years 2 weeks ago #866

  • Mike Adams
  • Mike Adams's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 2
I was confused by this as well as 1 and 4 would appear to be valid options.

Is it number 1 because the SPi is so high (relatively speaking) that a project wouldn't be that far ahead of schedule in the real world, so must have been terminated early?

Re:Need help on Oliver Lehmann Question 15 years 2 weeks ago #889

  • Hassan Abu-Baker, PMP
  • Hassan Abu-Baker, PMP's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 0
I had the same problem with this question from Lehmann.
according to Lehmann, the answer is "1" but no justification is provided..
I still don't get what is "post-mortem analysis" tho looked it up :huh:

Anyways, hope I'll pass, my exam is next week.

Hassan.

Re:Need help on Oliver Lehmann Question 15 years 1 week ago #915

  • Subayu Mandal
  • Subayu Mandal's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
1. The question states 'post-mortem' - > that means the project was closed.
2. At the successfull close of a project SPI should be 1.00 that is EV = PV.
3. For a successfully ended project EV cannot be greater than or less than PV.

Combining the above three - we get the reason for 'abruptly closed'.

Regards,
Subayu
Regards,
Subayu Mandal

Need help on Oliver Lehmann Question 1 year 11 months ago #30089

  • hi Praveen,
  • hi Praveen,'s Avatar
  • Visitor
  • Visitor
if you were referring to oliver lehmann 180 questions pdf, i found two more wrong answers, would you like to connect to discuss
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login