Regarding 15 questions which i receive from you every day. Please consider doubts on following question
Which of the following elements of developing HR Plan would give you extra consideration
A) Quality assurance activities

Budget control activities
C) Activity resource requirements
D) Risk management activities
My initial hunch was A instead of C which is the correct answer.
If i understand the question properly, it is questioned that which component of HR plan will save you most money .. Right? Please confirm.
Now based on this assumption, i think mending and correcting QA activities will make sure that Project work is done in most correct fashion to reduce cost of non conformance.
Please explain .. am i thinking too much or what