fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Changes affecting project constraints

Changes affecting project constraints 6 years 6 months ago #14256

  • Michael Haynes
  • Michael Haynes's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
I've seen a couple questions in the sim that seem to say opposite things. If I'm proposing a change, would I evaluate the effect on other project constraints before sending the change request in order to make sure the full effect of the change is understood by the CCB, or would I submit the change request first so that it is documented and I have a basis to look at the effect on project constraints

Thanks

Changes affecting project constraints 6 years 6 months ago #14258

  • Ty Weston, PMP
  • Ty Weston, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 207
  • Karma: 1
  • Thank you received: 37
Good question, and I know of companies that have done both, but my opinion is to understand the entire problem first, then submit a change request.
I believe it is important understand and document all the impacts onto the form, though I have seen complex forms and simple e-mails used.
I have believed I you should be able to speak to an issue intelligently prior to starting some kind of fire in the process. It has always seemed odd to me to start a fire in a process then not be able to explain it; it gets folks all worked up for no reason.
Other PMs may have another opinion.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login