fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Confusion about Resource leveling and Critical Chain method

Confusion about Resource leveling and Critical Chain method 6 years 8 months ago #13613

  • Vipasha Koul
  • Vipasha Koul's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
As per PMBOK
Resource levelling is used when shared or critical resources are only available at certain times or in limited quantities or over allocated
Critical Chain method is used to account for limited resources and project uncertainties

In Mock exam 7, a question asked is which tool should we use when we need to prepare schedule based on limited resources.

if Answer is Critical Chain Method then when resource levelling can be used for resource limitation as mentioned above in PMBOK ?

what am I missing ?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login