TOPIC: L04.05 PICC

L04.05 PICC 6 years 9 months ago #13285

  • Mahabubur Rahman
  • Mahabubur Rahman's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
I was just trying to figure out if any one noticed "Work performance information" is mentioned as an input to PICC in the above episode of pmprepcast .
As I have seen in the PMBOK it is written as "Work performance reports".

I will appreciate if anyone could clarify whether this right or wrong?

Best regards,

Mahabub

L04.05 PICC 6 years 9 months ago #13286

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1998
  • Karma: 121
  • Thank you received: 621
Please see page 100 of the Student Workbook where we say this in the Errata:

L04.05
21:25 23:38
We discuss Work Performance Information as the 2nd input to this process. However the correct input is Work Performance Reports.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login