TOPIC: Why isn't the Project Management Plan in input to Plan Stakeholder Management?

Why isn't the Project Management Plan in input to Plan Stakeholder Management? 6 years 9 months ago #13117

  • Summer Ruckman
  • Summer Ruckman's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 2
  • Thank you received: 0
Why is the Project Management Plan an input to the planning process of all the knowledge areas (from Scope to Procurement) but it is not for Stakeholder Management?

Why isn't the Project Management Plan in input to Plan Stakeholder Management? 6 years 9 months ago #13179

  • Steven Mudrinich, PMP
  • Steven Mudrinich, PMP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 126
  • Karma: 7
  • Thank you received: 25
Summer,

I suggest taking a look at the PMBOK Guide page 399. It very clearly states that the Project Management Plan is an input to Plan Stakeholder Management.

If you're thinking its not an input to Identify Stakeholders, you're correct. That is because stakeholders are usually identified before the Project Management Plan is created, but after you as the PM have a project charter and other business documents to start the planning process.

- Steven
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login