fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Does the Define Scope process create Change Requests

Does the Define Scope process create Change Requests 6 years 11 months ago #12684

  • Anil Gidwani
  • Anil Gidwani's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 0
Since the Scope baseline does not exist at the time Define Scope is executed, there is no question of a Change Request required for, for example, changing the requirements documentation due to findings during the scope definition.

Byt PMBOK 5 says (page 132) in Project Documents Updates: If approved change requests result from the Create WBS process, then the requirements documentation may need to be updated to include approved changes.

Very ambiguous, I think. Shouldn't the Create WBS process have Change Requests as an output according to the above statement?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login