fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Discrepancies in Achieve PMP Exam Success Book

Discrepancies in Achieve PMP Exam Success Book 6 years 11 months ago #12630

  • Abi Badiru
  • Abi Badiru's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
In the Achieve PMP Success book for CPM calculation it states that first day is Day 0 and the successor activity's ES is equal to the predecessor's EF. But in the PMPreCast it states that the first day as Day 1 and the successor activity's ES is equal to the predecessor's EF +1. Which method is accurate for the exam?

Also the Achieve PMP book has a question on Risk Attitude which is not in the PMBOK or the PMPreCast.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login