TOPIC: Workaround and change request

Workaround and change request 6 years 11 months ago #12580

  • Haitham M
  • Haitham M's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Hi
Once the workaround was applied for unidentified risk, should we submit a change request after implementation the workaround to include the cost incurred to the baseline? or just record it in the Lessons learned as it was done through the management reserve?

Workaround and change request 6 years 11 months ago #12582

  • John Wolverton
  • John Wolverton's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 118
  • Karma: 1
  • Thank you received: 27
Normally the change request is submitted before the workaround is implemented. Sometimes management would accept the consequences of the risk over the cost of the workaround. If it was an identity risk and the mitigation was identified in the risk plan then you could apply the workaround without a approved request. Either way I would then write it up in the Lessons Learned.
John F. Wolverton, PMP®

Workaround and change request 6 years 11 months ago #12583

  • Haitham
  • Haitham's Avatar
  • Visitor
  • Visitor
Hi
What I meant in my question that should the cost of workaround be added to the project cost baseline ( adjust the BAC to include any workaround cost through change management ) or there is no need to update the baseline as it is (BAC)not contained any management reserves expenditures
Thanks

Workaround and change request 6 years 11 months ago #12584

  • John Wolverton
  • John Wolverton's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 118
  • Karma: 1
  • Thank you received: 27
Baseline cost should not be changed unless you rebaseline the entire program. The cost would come out of management reserve or other contingency spending and be reflected there. Remember that the baseline is your reference point for the whole program, don’t change it, it tells you how good or bad you’re doing on the program.
John F. Wolverton, PMP®
The following user(s) said Thank You: Haitham M

Workaround and change request 6 years 11 months ago #12585

  • Haitham M
  • Haitham M's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Thanks for your quick response
In PMBook 7.2.2.6 reserve analysis the book reefer to the following
((When the amount of management reserves is used to fund unforeseen work, the amount of management reserve used is added to the cost baseline, thus requiring an approved change to the cost baseline.))
this was noted in page 206. could you please clarify?
Thanks again

Workaround and change request 4 years 11 months ago #19218

  • Trecia
  • Trecia's Avatar
  • Visitor
  • Visitor
Identified risk does not use workaround, it uses the contingency reserve.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login