fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Analogous vs Parametric Estimating

Analogous vs Parametric Estimating 6 years 11 months ago #12485

  • Laura K
  • Laura K's Avatar Topic Author
  • Visitor
  • Visitor
Analogous and parametric are both based on historical data. The PMBOK definition says parametric uses an algorithm and produces a higher level of accuracy. Is there something different about the source data used for the estimate? Why is it more accurate? I'm curious how people would define the difference between these two?

Analogous vs Parametric Estimating 6 years 11 months ago #12488

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 134
  • Karma: 7
  • Thank you received: 46
Hi Laura,

Analogous estimations are higher level and the estimate is a very broad stroke. "This project is very much like the ABC Project... The estimate for that project was $XXX, so we can use that." So, the estimate for the project is based on a similar project.

Parametric estimates are based on an algorithm/ formula and generally require a bit finer breakdown of the project tasks(at least, compared to an analogous estimate) in order to arrive at the estimate. For example, "This project entails the creation of 10 new reports for the customer. 4 are of low complexity, 5 are of medium complexity and 1 is highly complex." Experience has shown that the effort can be estimated as 10 hours per low complexity report, 20 hours per medium complexity reports and 30 hours for highly complex reports. Thus, the estimate for this project would be 4*10 + 5 * 20 + 1*30 = 170 hours.

In the parametric example, you can see that more work had to take place in order to get an estimate, since the work had to be more defined than in the analogous estimate.

I hope this helps!

Best regards,

Tracy
Forum Moderator
PMP, CSM, M.S. Management
The following user(s) said Thank You: Chuka Akunna

Analogous vs Parametric Estimating 6 years 4 weeks ago #15503

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
Why is parameteic a better way of estimating cost than analogous estimating?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login