fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Change requests - a project document?

Change requests - a project document? 7 years 1 month ago #12226

  • Anil Gidwani
  • Anil Gidwani's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 0
The Plan Risk Response process has the following output:

Project Documents Updates

which lists as one of its components "Change Requests"! (PMBOK v.5, page 348)

My question:

(1) Are Change Requests Project Documents?
(2) Why not simply make them a separate output of this process, as is done for other processes? Why include change requests in project documents?

Is this an evolving area of the PMBOK?

Change requests - a project document? 7 years 1 month ago #12272

  • Steven Mudrinich, PMP
  • Steven Mudrinich, PMP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 126
  • Karma: 7
  • Thank you received: 25
Anil,

Change requests are project documents, typically consolidated into a change log and electronically stored in most modern change control systems. I can't speak to why the PMBOK Guide doesn't separate it out; it doesn't matter for the exam, simply know that the CCS is used to monitor and control the changes to the project baselines.

- Steven
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login