fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Perform Integrated change control ( PICC)

Perform Integrated change control ( PICC) 7 years 1 month ago #12216

  • Christoph Farrenkopf
  • Christoph Farrenkopf's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
According PMBOK 5th edition, the PICC involves also "managing changes" ..but in explanation of Questions ID 12954 ( PM Prepcast simulator Question ID 12954) managing changes is excluded within PICC and should only be done within "Direct & manage Project Work" .

Per POMBOK , "Direct & manage Project Work" only talks from "Implementing approved changes". Is that the same as "managing Approved changes ?... quite confusing...
Whats right ? whats wrong ? Is there a deeper resolution of this Issue ?
Attachments:

Perform Integrated change control ( PICC) 7 years 1 month ago #12229

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 134
  • Karma: 7
  • Thank you received: 46
Hi Christoph!

In PMBOK 5 we have:


4.3 Direct and Manage Project Work
Direct and Manage Project Work is the process of leading and performing the work defined in the project
management plan and implementing approved changes to achieve the project’s objectives. The key benefit of this
process is that it provides overall management of the project work. The inputs, tools and techniques, and outputs
of this process are depicted in Figure 4-6. Figure 4-7 depicts the data flow diagram of the process.


"Managing the approved changes" is the only logical choice for the question you cited. Once approved, the request moves into the purview of those responsible for actually making it happen.

Even if one thinks that updating the change request should happen after the change is completed, this would be a function of managing the change request, not of managing the change itself.

I hope this helps clarify for you!

Best regards,

Tracy
Forum Moderator
PMP, CSM, M.S. Management
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login