TOPIC: PMIS quesion

PMIS quesion 7 years 2 months ago #11969

  • Scott Smith
  • Scott Smith's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 12
  • Thank you received: 0
For the Integration end of section quiz, one of the questions (9) asks which of the following are not part of the project management plan. The correct answer is the Issue log. However, option A is the "project management methodology." If I am correct, the project managment methodology is part of PMIS. PMIS is an EEF and also not part of the project management plan, right?