fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: PMP - Decision Tree Question

PMP - Decision Tree Question 7 years 2 months ago #11679

  • Monique Maxmillion
  • Monique Maxmillion's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $650,000 and B will cost U.S. $467,000. There is a
56% chance that project A will be successful, which will result in a gain of U.S.
$1,800,000. If project A fails there will be a loss of U.S. $900,000. There is a 67%
project B will be successful, and that will result in a U.S. $950,000 gain. If Project B
fails there will be a loss of U.S. $670,000. Based on this information, what is the
value of the best alternative?
A. U.S. $-38,000
B. U.S. $38,000
C. U.S. $-51,600
D. U.S. $51,600

PMP - Decision Tree Question 7 years 2 months ago #11687

  • Aung Sint
  • Aung Sint's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 37
  • Karma: 1
  • Thank you received: 8
Dear Monique,

The answer should be choice A: US$-38,000.

You need to calculate the EMV of Project A and B, and select the highest gain (more +) or the lowest loss (less -) between EMV of Project A and B.

EMV of Project A = -650,000 (cost) + 56% x 1,800,000 (success) - 44% x 900,000 (failure) = -38,000
EMV of Project B = -467,000 (cost) + 67% x 950,000 (success) - 33% x 670,000 (failure) = -51,000

Since -38,000 is bigger than -51,000, this is the answer.
Best regards,
Aung K. Sint, PMP
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login